There
seems to be absolutely no confirmation of the story below from a
mainstream TV network. They do, however, identify why the operation
should not happen. The NHK report below, is from about the morning of the 15th (GMT)
Japan postpones removal of Fukushima atomic fuel rods
Sources have told me — within Tokyo Electric — that they have no confidence that there’s any boron left between these fuel bundles. And they need boron to prevent the nuclear fuel from becoming a self-sustaining chain reaction, a criticality. So without boron in the plates — there are plates between these fuel bundles — but they got extraordinarily hot from not being cooled off the better part of a couple weeks, and they also were exposed to salt water. So that combination likely stripped out the boron. So the only thing Tokyo Electric can do is throw all sorts of boron into the water. Then pull the fuel. […]
Japan postpones removal of Fukushima atomic fuel rods
15
October, 2013, 14:40 CET
The
operators of the crippled Fukushima nuclear plant have postponed the
extremely complicated and difficult task of removing damaged atomic
rods.
New
video footage from a robot has revealed new leaks within the damaged
reactors meaning the rods now can’t be taken out as planned.
One
of the fuel assemblies was damaged as far back as 1982 when it was
mishandled during a transfer and is bent out of shape.
Kazuaki
Matsui, the executive director of Japan’s Institute of Applied
Energy said: “It’s very difficult to remove a spent rod because
parts of the wall and the bottom of the reactor are all melted. We’ve
never had to deal with this before so that adds to the complication.”
Meanwhile,
decontamination workers say mismanagement is to blame for the delay
of radiation removal work.
The
inital plan called for the clean-up in the affected towns to be
finished by March this year but the government now says the work will
be delayed by as much as three years.
Fuel
rod removal set to start at Fukushima plant
The
operator of the Fukushima Daiichi nuclear power plant plans to take
the first step in decommissioning the facility next week, more than 2
and a half years after its triple meltdown.
NHK,
Nov.
15, 2013 - Updated 10:33 UTC
Tokyo
Electric Power Company, or TEPCO, said on Friday that workers will
start removing nuclear fuel rod units from a storage pool at the
plant's Number 4 reactor on Monday.
The
pool holds more than 1,500 units, including some that are extremely
radioactive and spent and others that are unused. The reactor holds
the most units of any at the plant.
In
March 2011, a hydrogen explosion severely damaged the building of the
reactor. But unlike 3 other reactors at the plant, it did not suffer
a meltdown as its pressure vessel was empty.
TEPCO
officials say nuclear regulators and outside experts have found no
problems with the firm's preparation to cover the damaged building
and install a crane to remove the fuel.
Workers
plan to transfer the units into a cask in the pool, use the crane to
lift out the cask, and transfer the fuel to an outside storage pool
about 100 meters away.
TEPCO
has 2 casks that can each hold up to 22 units. Workers are to fill
the first cask with less radioactive unused fuel. Removal of all the
rods is expected to take until late next year.
Safety
is a major concern in the project -- the first milestone in an
unprecedented decommissioning process that could span 4 decades.
The
reactor pool is still littered with small debris that could hamper
smooth removal of the units.
The
job will require extreme caution, as any damage to the fuel or casks
could unleash high-level radiation.
If
trouble occurs, workers' exposure could reach the safety limit,
seriously setting back the removal process
Gundersen:
Fuel already “very close to going critical” at Unit 4
Must
be extraordinarily careful about starting chain reaction
Fairewinds
Chief Engineer Arnie Gundersen,
Coast to Coast AM with John B. Wells, Nov. 9, 2013 (at
31:30 in):
Sources have told me — within Tokyo Electric — that they have no confidence that there’s any boron left between these fuel bundles. And they need boron to prevent the nuclear fuel from becoming a self-sustaining chain reaction, a criticality. So without boron in the plates — there are plates between these fuel bundles — but they got extraordinarily hot from not being cooled off the better part of a couple weeks, and they also were exposed to salt water. So that combination likely stripped out the boron. So the only thing Tokyo Electric can do is throw all sorts of boron into the water. Then pull the fuel. […]
I
ran a division that built fuel racks, and these high density fuel
racks like they have a Fuksuhima are very close to going critical
anyway. […] Normally its .95, as high as .99, that means there’s
a 1% margin before a self-sustaining chain reaction can occur. The
problem there is that the fuel pool doesn’t have the ability to
remove the heat if these nuclear fuel bundles turn back.— a
criticality means they turn back on outside of the nuclear reactor.
So they have to be extraordinarily careful that they don’t start a
chain reaction in the fuel pool […] If they get close together you
can cause a chain reaction, and what will happen then is the water
will begin to boil violently. Hopefully Tokyo Electric is going to be
monitoring this really closely and the first indication of water
bubbling, they push the rods back in. The problem though is that the
rack is distorted and as you pull it, you’re pulling way more
friction than it was designed to handle. It’s a real problem.
Reactor no. 1 -
Fukushima
Watch: Remote-Controlled Boat Gives Glimpse of Damaged Reactor
Building
WSJ,
15
November, 2013
The
operator of the stricken Fukushima Daiichi nuclear power plant has
for the first time confirmed that water is indeed leaking from the
badly damaged No. 1 reactor vessel to the building that houses the
unit by using a small remote-controlled boat.
While
the upcoming removal of fuel rods from the No. 4 reactor building has
received global attention in recent weeks, much more difficult tasks
lay far ahead: Cleaning up the melted down No.1-3 reactors.
The
job will be a huge challenge because these units are so highly
contaminated that no one, even in a protective suit, can enter the
building.
Given
that almost all work in and around the Nos. 1-3 reactors would have
to be done by remote controlled robots, the success in using the
camera-equipped boat “is a big step forward,” said a spokesman
for Tokyo Electric Power Co.
It
has long been assumed that the No. 1 reactor vessel has been leaking
since 400 metric tons of water is needed daily to keep the core from
being exposed. But there had been no direct confirmation until the
latest remote-controlled inspection.
The
water in the reactor buildings, which becomes highly radioactive due
to the high level of damage to the nuclear fuel, is currently being
pumped out of the building and processed. Part is reused to cool the
reactors, while the rest goes through another process to remove most
radioactive materials and stored in tanks.
One
of the difficulties in using robots in the complex decommissioning
project is that one robot can generally undertake one specific task.
Since there are numerous challenges, each step may require
development of a new technology.
For
example, Tepco plans to search the off-limits No. 2 and No. 3 reactor
buildings, but the spokesman said the company is not sure if the same
boat can do the job.
The
Japanese government has so far provided about ¥94 billion ($939
million) for development of new decommissioning technologies
including remote-controlled robots. The current boat was made by
Hitachi Ltd., one of the makers of the Daiichi plant’s reactors.
“There
are many technologies not yet developed,” said Lake Barrett, a
U.S.-based nuclear consultant who was the senior regulatory official
in charge of the cleanup of the Three Mile Island nuclear plant in
Pennsylvania. “But I don’t think they are undevelopable,” said
Mr. Barrett, who is currently advising Tepco in relation to the
decommissioning.
Nuclear
Engineer: New
footage shows Reactor 1 has
“ruptured” containment
structure, most likely from
the explosion
Water
to cool “what’s left of core” flowing into environment (VIDEO)
15
November, 2013
The
Japan Times,
Nov. 14, 2013: One leak came from a rupture in a sand-cushioned drain
pipe installed at the bottom of the containment vessel.
Chris
Harris, former licensed Senior Reactor Operator and engineer,
Nutrimedical Report, Nov. 14, 2013 (at
29:00 in):
They did indeed find water pouring out of several locations in
Reactor 1′s containment structure and basically this shows
that it was ruptured, most likely during the explosion that happened
[...] As we discussed before, all the water that gets pumped in to
cool what’s left of the core [...] it goes in and it’s falling
back out again and goes right into the secondary side, which is
basicallly the reactor building [...] Because the water level’s not
going up into that part of the building, it’s flowing out into the
environment. That’s not really good news.
No comments:
Post a Comment
Note: only a member of this blog may post a comment.