Some
Fukushima fuel rods were damaged before 2011 catastrophe
Three
of the spent fuel assemblies that will be pulled from the Fukushima
nuclear plant during a year-long operation were damaged before the
2011 earthquake and tsunami crippled the Japanese facility.
RT,
15
November, 2013
Tokyo
Electric Power Co. (TEPCO), which operates the plant, said the
damaged assemblies - 4.5 meter high racks with 50 to 70 rods of
highly irradiated used fuel - won’t be lifted from the plant’s
Reactor No. 4 when a large steel chamber, or cask, is employed to
move over 1,500 assemblies to safe storage, Reuters reports.
In
an 11-page information sheet released in August, TEPCO said one of
the assemblies was even damaged as long ago as 1982, when it was bent
out of shape during a transfer.
In
2010, TEPCO said that another two spent fuel racks in the reactor’s
cooling pool possibly contained wire trapped in them. Rods in the
assemblies have small cracks and are leaking low-level radioactive
gases, TEPCO spokesman Yoshikazu Nagai told Reuters on Thursday.
The
damaged racks were first reported by a Fukushima area newspaper on
Wednesday, as TEPCO is preparing to decommission the plant and remove
the spent fuel assemblies from Reactor No. 4.
"The
three fuel assemblies...cannot be transported by cask," TEPCO
spokeswoman Mayumi Yoshida told Reuters in an email response on
Thursday. "We are currently reviewing how to transport these
fuel assemblies to the common spent fuel pool."
TEPCO
is set to begin removing 400 tons of the hazardous spent fuel, an
unprecedented operation, beginning in mid-November.
The
damaged assemblies will only make the job more difficult, and could
meddle with the year timeframe that TEPCO has set for removal –
which is already an ambitious plan to many.
TEPCO
is in the process of decommissioning the entire six-reactor Fukushima
Daiichi plant after three reactors suffered core meltdowns in March
2011. Moving the fuel assemblies in Reactor No. 4 is the first
priority, as their height above ground - 18 meters - is highly
vulnerable to another earthquake.
Former
US nuclear regulator Lake Barrett, who is advising TEPCO, visited the
plant Wednesday and endorsed the preparations for the No. 4
assemblies.
"While
removal of the fuel is usually a routine procedure in operating a
power plant, the damage to the reactor building has made the job more
complex," he said.
He
added that he was "genuinely impressed by the thoroughness of
the effort and TEPCO's contingency planning."
The
fuel assemblies will be lifted - all while submerged in water to
prevent overheating - from storage frames in the pool and placed in
the cask. Once the 90-ton cask is filled, it will be lifted from the
pool by crane, set on the ground, and transported to a storage pool
nearby.
Robot detects locations of radioactive leaks at crippled Fukushima nuclear plant
For
the first time, a remote-controlled robot has detected the exact spot
of radioactive water leaks from the crippled Fukushima nuclear
plant’s Reactor 1, local media reported.
RT,
14
November, 2013
The
robot was sent close to the lower part of the Reactor 1 containment
vessel at the wrecked Fukushima Daiichi on Wednesday. Its camera
captured images of radioactive water leaking from two holes of the
vessel into the building housing the reactor, NHK television
reported.
The
lower section of the vessel contains water that cools the molten
nuclear fuel rods, damaged after the March 2011 earthquake that
triggered a tsunami which hit the Fukushima nuclear facility.
The
radiation levels in the inspected area were reported at 0.9 to 1.8
sieverts an hour, while a typical release of radiation is generally
accepted to be 1 millisievert a year.
Tokyo
Electric Power Company (TEPCO), the nuclear plant’s operator
responsible for the cleanup, has to keep the melted uranium fuel rods
of the three damaged reactors cool for them to be relatively stable.
Thus, the operator is storing huge amounts of radioactive water at
Fukushima nuclear facility.
However,
TEPCO engineers said that they cannot estimate the amount of water
that leaked through the holes, NHK reported. They also admitted that
Reactors 2 and 3 of the Fukushima Daiichi have similar problems.
TEPCO
is now planning to use robots to locate other leaks which have been
causing concern, as it is important not only in solving water
contamination problems but also in carrying out decommissioning of
the reactors.
This
handout picture taken by Tokyo Electric Power Co (TEPCO) on November
13, 2013 shows US nuclear expert Lake Barrett and TEPCO workers
inspecting the spent fuel pool at the unit four reactor building of
the crippled TEPCO's Fukushima Dai-ichi nuclear plant at Okuma town
in Fukushima prefecture. (AFP Photo/TEPCO)This handout picture taken
by Tokyo Electric Power Co (TEPCO) on November 13, 2013 shows US
nuclear expert Lake Barrett and TEPCO workers inspecting the spent
fuel pool at the unit four reactor building of the crippled TEPCO's
Fukushima Dai-ichi nuclear plant at Okuma town in Fukushima
prefecture. (AFP Photo/TEPCO)
Earlier
in November, TEPCO announced that by the end of the month the company
will start extracting more than 1,500 fuel rods from the No 4 reactor
of the crippled nuclear plant, which contains 10 times more
Cesium-137 than Chernobyl did.
The
rods are expected to be placed in the outdoor pool at the station by
the end of next year.
However,
scientists have urged caution as such an operation has never been
undertaken, while a mishap could release a huge amount of radiation
into the atmosphere or cause an explosion many times worse than the
original disaster.
“If
something goes wrong this could be a global catastrophe that dwarfs
what has happened in Fukushima Daiichi thus far,” Kevin Kamps, a
nuclear waste specialist from the organization Beyond Nuclear told
RT.
According
to experts, complete elimination of the consequences of the nuclear
catastrophe will take from 30 to 40 years.
The
crippled reactors of the nuclear facility are located near the coast
of the Pacific Ocean. After the tsunami that hit Fukushima, the cores
of the three reactors melted and burnt through the concrete basement
of the reactor zone. The water used to cool them has been leaking
into the soil and contaminating the ground water on the premises of
the nuclear facility. This water eventually started seeping into the
Pacific. According to estimations from Japan’s Ministry of
Industry, around 300 tons of contaminated groundwater has leaked into
the ocean daily since the nuclear disaster occurred in 2011.
Fukushima
Workers Say Decontamination Not Working! They're Afraid To Even Wash
Their Hands!
Risky
fuel removal about to start
The
decades-long decommissioning process at the crippled Fukushima No. 1
plant is about to take what Tokyo Electric Power Co. says is “an
important step,” as the utility starts removing fuel rod assemblies
from the spent fuel pool high up in reactor building 4 sometime this
month.
14
November, 2013
Moving
the massive amount of radioactive fuel assemblies out of the
shattered building is significant because it will allow Tepco to
monitor the fuel much more easily at another pool in an undamaged
facility, experts say.
Meanwhile,
they stress the task must be handled very carefully to avoid dropping
and damaging the assemblies.
“Usually,
spent fuel rods are safely stored in sturdy reactor buildings, but
reactor building 4 experienced a hydrogen explosion, so it has lost
its full containment capability,” said Kiyoshi Takasaka, an adviser
on nuclear issues to Fukushima Prefecture.
The
hydrogen blast occurred March 15, 2011, four days after the
earthquake and tsunami, blowing the roof off the building and
showering debris into the pool.
The
pool has 1,533 fuel rod assemblies, 202 of which are unused. Once
removed from the pool, the assemblies will be stored in a common pool
in a different building.
Each
assembly, a zirconium alloy box, is about 4.5 meters long and
contains 60 to 80 fuel rods.
A
fuel handling machine, which is like a hoist, set up over the pool
will lift the assemblies one by one and place them into special
transport casks. The casks will be put into the pool ahead of time,
so that this work is done underwater to prevent gamma radiation from
spilling to the outside environment.
Each
cask can store 22 assemblies. A crane installed above the fuel
handling machine will load them onto a trailer for transport to the
common pool.
If
all goes well, removing all of the assemblies will take about a year.
Tepco said it is using nearly the same removal equipment used for
regular nuclear operations.
Lake
Barrett, a special adviser to Tepco who was in charge of the cleanup
work after the Three Mile Island nuclear accident in the U.S., said
he visited the plant Wednesday and was impressed with Tepco’s
preparations.
Building
4 has been reinforced with steel frames and a cover, the equipment is
in place and the workers have been trained well for the operation,
Barrett said.
“Now
I feel confident that they can complete this job properly,” he
said, adding that the level of Tepco’s preparations will make the
operation almost like a normal fuel removal.
Still,
it will be different than performing this operation in an undamaged
building, and extra caution is a must.
For
instance, engineers normally program coordinates into the fuel
handling hoist and let it run automatically, but they will manually
control it for this operation.
Takasaka
said it is essential that the people in charge of the task have
enough training in handling the manual operations.
He
added that although Tepco has been picking debris out of the pool,
there are still small pieces that could fall between the assemblies
and racks that contain the assemblies, possibly making it harder to
lift them or even breaking them.
Barrett,
who saw the pool for himself, said the water clarity is good but it
is true that the assemblies could get jammed by small debris.
Tepco
said it is ready for such eventualities. For instance, it plans to
use underwater vacuum cleaners as much as possible.
Also,
if the hoist detects extra weight when removing the assemblies, it
will stop moving to avoid forcing the assemblies.
Another
risk is dropping the assemblies and damaging them.
“It
is imperative not to drop the assemblies when removing and after
removing them from the racks,” said Hisashi Ninokata, a nuclear
expert and professor at Polytechnic University of Milan in Italy.
“In
the worst-case scenario, dropping a cask is conceivable. To avoid
that, it is important to come up with multiple layers of measures,”
said Masayuki Ono, a Tepco spokesman.
For
instance, the crane’s control wires have been doubled, and it is
designed not to drop the assemblies if the power is cut off, Tepco
says.
And
if an assembly is dropped and gets damaged enough to release
radioactive materials, the radiation level outside Fukushima No. 1
will still not exceed the legal limit, the utility claims. This
estimation is based on a scenario in which one assembly falls and
strikes others, resulting in damage to all of the fuel rods contained
in two assemblies.
Earlier
this week, Tepco found three damaged assemblies that will be
difficult to remove, but officials said the damage appeared to have
occurred before the March 11 disasters.
Ninokata
feels that as long as Tepco is sufficiently prepared and proceeds
carefully, it is hard to imagine that any assemblies will get
damaged, but if this does happen, he agrees with the utility that
harmful amounts of radioactive materials won’t escape into the
environment.
Asked
if it’s possible for the spent fuel to achieve recriticality, Zengo
Aizawa, vice president of Tepco overseeing the Fukushima crisis, said
this is highly improbable since the removal process basically deals
with one assembly at a time, and the utility has confirmed that one
assembly alone cannot cause a nuclear chain reaction.
Thyroid
cancers up in Fukushima
Experts
say link to disaster not yet established
13
November, 2013
Screening
of Fukushima residents who were 18 or younger at the time of the 2011
nuclear disaster had found 26 confirmed and 32 suspected cases of
thyroid cancer as of Sept. 30, according to the Fukushima Prefectural
Government.
The
number of confirmed cases was up by eight from August, while the
suspected cases rose by seven, the prefecture-led study found.
About
226,000 people have undergone the screening program since it kicked
off in October 2011.
The
26 confirmed cases underwent surgery and are doing well, according to
the prefecture.
A
panel of experts at the prefecture concluded Tuesday that it is too
early to link the cases to the nuclear disaster, given that papillary
thyroid cancer — the type found in the 26 people — develops at a
very slow pace, according to prefectural officials. Following the
1986 Chernobyl catastrophe, it took about four to five years for
thyroid cancers in significant number to be detected.
Thyroid
cancer is considered a major health concern for children because
radioactive iodine spewed by the crippled nuclear plant tends to
accumulate in thyroid glands, especially among young children.
Following
the Chernobyl disaster, more than 6,000 children were diagnosed with
thyroid cancer, according to the U.N. Scientific Committee, which
attributed many of the cases to consumption of contaminated milk.
According
to media reports, thyroid cancer normally strikes about 1 to 2 people
aged 10 to 14 per million in Japan, far less than about 115 in 1
million cases in Fukushima. However, the figure cannot be simply
compared, because the screening in Fukushima targets all children
under 18, most of whom are without any symptoms, and no such
screening is being done elsewhere in Japan.
To
address mounting worries among local residents with children, the
prefecture will expand the screening tests next April to include
people born after the disaster started.
No comments:
Post a Comment
Note: only a member of this blog may post a comment.