Utility
investigating vibrations that caused shutdown of nuclear reactor
Idled
unit was being restarted when vibrations occurred
11
May, 2013
Dominion
Virginia Power had a crew of about 20 working Friday to determine
what caused the shutdown of its North Anna power facility’s Unit 2
nuclear reactor earlier in the day.
The
unit was idled April 7 for a scheduled refueling.
The
utility was in the process of restarting it, and the unit was at 60
percent power shortly after 6 a.m. Friday, when operators detected
greater-than-normal vibrations in part of the mechanism used to start
the reactor. They manually shut it down.
The
excessive vibrations were detected in the exciter, which is used
during start-up to initiate the flow of electricity from the
generator to the grid. The exciter spins with the turbines and
electric generator on one long shaft.
“By
midafternoon our crews were able to get into the enclosure around the
exciter to begin more detailed troubleshooting,” said Dominion
Virginia Power
spokesman Jim Norvelle. “This is a high-voltage area
with exposed parts spinning at 1,800 rpm at the end of the turbine
generator shaft. The team had to wait until the shaft stopped
spinning.”
He
said they were working to determine if the issue is a mechanical or
an electrical problem.
Norvelle
said the crew working on the unit is a mix of Dominion Virginia Power
employees, contractors and technicians from Siemens, the equipment
supplier.
He said the crew members were on site for the refueling
outage that ended Thursday when the unit had returned to service.
Norvelle
said the U.S. Nuclear Regulatory Commission was notified of Friday’s
shutdown.
Dominion
Virginia Power does not give estimates of when nuclear power units
will return to service, Norvelle said. Because of the mild weather,
“there’s very little demand out there right now,” he said.
The
North Anna nuclear power plant is along Lake Anna in Louisa County,
about 45 miles northwest of Richmond. The plant’s Unit 1 is
operating at full power, as are the utility’s other two nuclear
reactors in Virginia, at the Surry nuclear station along the James
River in Surry County.
Dominion
said refueling outages, which are typically scheduled every 18
months, are planned this fall at North Anna Unit 1 and Surry Unit 1.
Radioactive
Reality (11 May 2013) Terror drill at Fukushima nuclear plant
No comments:
Post a Comment
Note: only a member of this blog may post a comment.