Nuclear
waste clean-up delayed and billions over budget
The
new Secretary of Energy has been on the job only four weeks, but he
made a beeline Wednesday to see his biggest headache for himslf.
Ernest Moniz went to the Hanford Nuclear Reservation in Washington
state
CBS,
19
June, 2013
Hanford
made the plutonium for American nuclear weapons from the Manhattan
Project in World War II until 1987. Now, highly radioactive waste is
leaking, and a project to clean it up has stalled.
The
clean-up at the Hanford Nuclear Reservation costs U.S. taxpayers $2
billion every year. This winter, engineers discovered six new leaks
of radioactive material from underground tanks.
"There's
something on the order of 1,000 gallons a year that are leaking now
from these six tanks," says Washington Gov. Jay Inslee.
The
government's clean-up plan involves pumping 56 million gallons of
waste out of 177 tanks, mixing it with liquid glass and sealing it in
canisters.
"That
does involve technological challenges that some people have
associated with the kind of leap that the moonshot involved,"
Inslee says. "This has never been done in human history before."
The
clean-up is supposed to take place at a $13 billion complex, but the
plant has been plagued with technical challenges since the project
began in 2000. Most of the problems are at the pre-treatment
facility.
There's
no activity at the building that is the first stop for the nuclear
waste once it's removed from the storage tanks. The Department of
Energy suspended construction about a year ago.
"They
did an analysis and identified over 100 single-point failures in the
pre-treat facility," says Donna Busche, a manager of
environmental and nuclear safety at Hanford.
Even
after billions of dollars have been spent, Busche says, "I do
not believe it will work as is."
Little
is known about what was put in the tanks and how it's changed since
the 1940s. Busche is worried it's unstable and an explosion during
clean-up could release radioactive material.
Asked
how a treatment facility can be built when it's unclear what is in
the tanks, Busche says, "I think that is the fundamental issue.
We don't understand the chemical reactions, but yet we're building
the plant."
Similar
concerns were raised in a review by the Government Accountability
Office, Congress' investigative agency. It blamed the Department of
Energy for building the plant before the design process was complete.
As a result, parts of the facility "may not work and may not
meet nuclear safety standards," the report said.
The
report was also critical of the Bechtel Corporation, the contractor
in charge of the project. "The scheduled completion date has
slipped by nearly a decade to 2019," it said. And the cost has
more than tripled to "$13.4 billion ... and could grow
substantially."
Bechtel
spokeswoman Suzanne Heaston gave us a tour, but not an explanation.
Asked
who is at fault for the plant's failure to be up and running, she
replies, "You'll talk to the Department of Energy about that."
On
Wednesday, Energy Secretary Ernest Moniz had this to say: "I
believe the problems -- what I've seen -- should be manageable. We
may have to make some changes in how we are approaching the project."
But
in the time it takes to come up with a new solution, Busche says,
"Waste will be leaking into the ground water. It will continue
to leak. It's an urgent problem that must be solved."
But
engineers have to get this right. It will take 40 years to treat the
waste, and during that time, radiation will make parts of the plant
inaccessible to humans.
No comments:
Post a Comment
Note: only a member of this blog may post a comment.