Another
radioactive leak found at Japan's Fukushima nuclear plant
A discharge of contaminated water has been discovered at the disabled Fukushima Daiichi nuclear plant. It is the latest in a string of incident hindering the clean up of the worst nuclear disaster since Chernobyl in 1986.
RT,
5
June, 2013
Tokyo
Electric Power Co (Tepco), the owner of the wrecked plant, said it
discovered the leak on Wednesday, fueling yet more criticism of the
company as it seeks permission to release water into the sea, Reuters
reported.
Shunichi
Tanaka, the head of Japan's new nuclear regulator, created after its
predecessor was discredited in the 2011 accident, told a news
conference that Tepco should deal with the situation “without
delay.”
Japan’s
regulator, however, did not regard the matter as serious, he added.
The
Fukushima Daiichi Nuclear Power plant suffered a reactor meltdown and
the release of radiation following the 9.0 magnitude Tokohu
earthquake - the most powerful earthquake ever to hit Japan - that
struck off the coast of Japan on March 11, 2011.
The
earthquake unleashed a tsunami with waves of up to 14 meters high
(Fukushima was designed to handle up to 5.7-meter waves) that knocked
out emergency generators required to cool the reactors.
Wednesday’s
setback comes after Tepco revealed this week it had detected
radioactive caesium in groundwater flowing into the plant,
contradicting an early finding that contamination levels around the
facility were negligible.
About
400 tons of groundwater flows daily into the reactor buildings, where
it is mixed with highly contaminated water used as coolant for the
melted fuel. The realization that groundwater is being contaminated
before it enters the damaged reactor units complicates Tepco’s
efforts to convince local authorities that the groundwater is safe
enough to be dumped into the ocean.
The
news also comes as a major political challenge to Prime Minister
Shinzo Abe, whose government is set on plans to export Japan's
nuclear technology.
The
government ordered Tepco last week to increase storage capacity of
water tanks and build earthworks around the four reactor buildings to
control the flow of groundwater seeping into the facility.
Leaks
were discovered in underground storage tanks in April, prompting
Tepco to speed up the construction of stronger above-ground
containers. The leak discovered on Wednesday was from one of the
sturdier tanks, Reuters reported.
The
power company is also seeking approval to dump 100 tons of
groundwater a day from the plant into the sea, a plan that requires
the consent of fishermen who are strongly against the idea.
On
May 30, Tepco told fishermen that radioactive caesium in the
groundwater was at a level that could not be detected.
But
the results were inaccurate as they were skewed by using procedures
that failed to take into account the background radiation at the
damaged plant, Tepco told Reuters on Tuesday.
"We'll
have to correct the way we analyse sample data," said Mayumi
Yoshida, a Tepco spokeswoman.
The
revised results continue to show radiation levels below what Tepco
views as the upper threshold for releasing groundwater - one
Becquerel of caesium per 137 per liter. A Becquerel is a measure of
radioactivity.
On
December 21, 2011, the Japanese government released a comprehensive
program for the clean up efforts, which predicted that the full clean
up will take 40 years.
TEPCO's
failure at math may have increased radiation release at Fukushima
plant
Workers miscalculated pressure levels inside a reactor during the early stages of the Fukushima nuclear crisis, leading to a reduction in cooling water and a possible increase in the volume of radioactive materials released.
June
05, 2013
By
TOSHIHIRO OKUYAMA/ Senior Staff Writer
Tokyo
Electric Power Co. estimated the pressure inside the No. 2 reactor
containment vessel at 400 kilopascals on March 16, 2011, five days
after the Fukushima No. 1 nuclear plant was crippled by the Great
East Japan Earthquake and tsunami.
The
actual pressure was 40 kilopascals, far below the 101 kilopascals of
the surrounding atmosphere, suggesting that a large amount of
radioactive materials escaped from the reactor.
TEPCO
later discovered the mistake but did not announce it. Instead, the
correct pressure figures were included in a deluge of information
released by the utility.
TEPCO
concluded that pressure was rising on the afternoon of March 16 and
halved the amount of water being injected into the No. 2 reactor on
the morning of March 17.
Tadayuki
Yokomura, chief of the company’s Kashiwazaki-Kariwa nuclear plant
in Niigata Prefecture, warned TEPCO officials against lowering the
water level later that morning.
“I
think the airtightness (of the containment vessel) has not been
maintained,” Yokomura said, according to a video footage of a TEPCO
teleconference.
However,
TEPCO further reduced the amount of water by midday, apparently
fearing that flooding the reactor could lead to a rise in pressure
that might cause an explosion.
TEPCO
increased the amount of water in the late afternoon of March 17
because some officials suspected that much of the injected water was
leaking out.
TEPCO
noticed the mistake in the pressure level when it reconfirmed data
more than a month later. The company said it cannot say whether the
mistake affected the situation.
“Radiation
levels were unchanged before and after the amount of water injected
was changed,” an official said.
The
No. 2 reactor was considered the most dangerous at the Fukushima No.
1 nuclear plant early in the crisis. Cooling functions were lost on
March 14, and the reactor melted down following the No. 1 and No. 3
reactors.
The
difficulty in venting fueled concerns that mounting pressure could
rupture the containment vessel and release lethal levels of
radioactive materials.
Early
on March 15, TEPCO temporarily evacuated all but the minimum required
70 or so workers from the plant compound.
Officials
were closely monitoring pressure levels inside the containment vessel
as an indicator of whether radioactive materials were contained
within the reactor.
At
TEPCO’s news conference on the afternoon of March 16, reporters
asked about the possibility that the containment vessel had already
lost airtightness due to structural damage, and that the pressure
inside had fallen to the level of the atmosphere.
Late
on the night of March 16, a TEPCO official told reporters that the
pressure was rising.
The
company presented data that showed the pressure had increased from
220-240 kilopascals earlier in the day to 400 kilopascals or more
between 7 a.m. and 2 p.m.
However,
the actual figure was 40 kilopascals from early morning through noon.
According
to TEPCO, workers thought the reading of a pressure gauge at the
central control room was either 40 or 400 kilopascals past noon.
However, they were unable to reconfirm the reading for fear of being
exposed to high radiation levels.
Instead,
workers calculated the pressure based on data from a system that
suspends reactor operations if it detects an abnormal pressure rise.
But they used a wrong conversion formula and erroneously concluded
that it was 400 kilopascals.
TEPCO
noticed the mistake in late April at the earliest. The company
included corrected pressure figures when it distributed a large
volume of electronic data--including figures for other reactors--at a
news conference on May 16, 2011.
TEPCO
officials did not clearly explain that the March 16 pressure data for
the No. 2 reactor had been corrected.
The
corrections went largely unnoticed. And the panels set up by the
government, the Diet and TEPCO to investigate the nuclear accident
failed to address the issue.
The
Asahi Shimbun independently analyzed the data for the No. 2 reactor
and has asked TEPCO to provide an explanation since April 2012.
“Workers
applied a wrong conversion formula while they were preoccupied with
dealing with the accident,” a TEPCO public relations official said.
The
official also indicated that there was no problem with the way the
corrected figures were disclosed.
“We
compiled and provided as much information as possible while giving
priority to recovery operations at the plant,” the official said.
No comments:
Post a Comment
Note: only a member of this blog may post a comment.